State rules

Building Codes and Permits in California

One statewide code, Title 24, adopted every three years by the Building Standards Commission and enforced by your city or county building department.

The codes California uses

California Building Standards Commission publishes the California Building Standards Code (California Code of Regulations, Title 24) every three years. Most states start from the International Code Council's model codes and add their own changes.

  • Building code (commercial and multifamily)

    2025 California Building Code (Title 24, Part 2)

    Based on 2024 International Building Code · in effect since January 1, 2026

  • Residential code (houses and duplexes)

    2025 California Residential Code (Title 24, Part 2.5)

    Based on 2024 International Residential Code · in effect since January 1, 2026

  • Electrical

    2025 California Electrical Code (Part 3)

    Based on 2023 National Electrical Code · in effect since January 1, 2026

  • Plumbing and mechanical

    2025 California Plumbing and Mechanical Codes (Parts 4 and 5)

    Based on 2024 Uniform Plumbing and Mechanical Codes · in effect since January 1, 2026

  • Energy

    2025 Building Energy Efficiency Standards (Part 6)

    Based on California's own (Energy Commission) · in effect since January 1, 2026

  • Green building

    2025 CALGreen (Part 11)

    Based on California's own · in effect since January 1, 2026

Coming next: The 2028 edition is due January 1, 2029. Permits applied for before January 1, 2026 could still use the 2022 code.

Who enforces the code

  • Your city's building department (or the county's, outside city limits) issues permits, checks plans and inspects the work.
  • State agencies handle a few kinds of buildings themselves: the Division of the State Architect for public schools, HCAI for hospitals, and HCD for manufactured homes and factory-built housing.
  • Local changes: Cities and counties may make the code stricter, but only with written findings about local climate, geology or terrain, filed with the state.

Your city or county building department is the place to ask what a project needs; its inspectors check permit work. About building inspectors in California.

Your county and city

Inside a city, the city's building department handles permits; in unincorporated areas (outside any city) the county's building department does. Many cities and counties adopt local amendments, such as stricter fire rules in wildfire areas, all-electric rules or extra earthquake requirements.

California doesn't publish one statewide list of building departments: search for your city's or county's "building department" or "permit center" on its official .gov site.

When you need a permit

Almost everywhere in California, these need a permit:

  • New buildings, additions, garages and accessory dwelling units (ADUs)
  • Structural changes: moving or removing walls, new window or door openings, beams, foundations
  • Most electrical, plumbing and heating or cooling work beyond simple repairs (new circuits, panels, water heaters, furnaces, AC units)
  • Re-roofing, decks more than 30 inches off the ground, pools and spas, solar panels, demolition

In California specifically

  • Replacing a water heater needs a permit; the inspector checks the earthquake straps and venting.
  • Most cities must decide an ADU application within 60 days of a complete application (state ADU law).
  • A contractor (or you, as an owner-builder) pulls the permit; check the contractor's CSLB license on this site first.

Usually no building permit

  • Painting, wallpaper, carpet, tile, vinyl and wood flooring, cabinets and countertops
  • Replacing a faucet or fixing a leak, and swapping a light fixture or outlet on an existing circuit (rules vary by state)
  • Small detached sheds and playhouses under the size limit, low fences and short retaining walls
  • One-story detached accessory buildings up to 120 square feet (California amends the model code's larger limit down)
  • Fences up to 7 feet and retaining walls up to 4 feet that hold back no extra load

Work that needs no permit still has to meet the code, and zoning, historic-district and homeowner association rules still apply. Your city or county can require more than this list, so check with its building department before you start.

Doing the work yourself

You can pull a permit for your own home as an owner-builder, but you take on the contractor's responsibilities, and hiring unlicensed workers can make you their employer for payroll and workers' comp. The city will ask you to sign the state's owner-builder form.

Which trades need a licenseWhat CSLB licenses, and what cities and counties license instead.Home and building inspectorsHow California handles inspectors.Find a licensed contractorLicense, bond and insurance checked against state records.

Official sources

Checked November 25, 2026 on the state agencies' own pages. Codes change every few years and dates can move; the state's own pages and your building department have the final word. This is general information, not legal advice.